6 min read · 1,422 words
This article was written with AI. It was drafted from the sources it cites and checked against the full text of those sources before publishing. How we make articles
Nearly 80 MW: the average new data center that entered service in 2025, against around 25 MW in 2020, according to research notes citing FERC market material (Abacus). If AI data center grid interconnection is the new GPU queue, October 9, 2026 is the day it got a rulebook: FERC approved PJM’s Large Load Registry, a mechanism to collect information on facilities drawing at least 50 MW at a single electrical site, and in the same order rejected the grid operator’s proposed curtailment framework (TechTarget).
PJM told FERC it hosts the largest concentration of data center load in the world and predicts 32 GW of load growth from 2024 to 2030, with 30 GW of that coming from data centers (Dominion Post). The same grid serves more than 67 million people across 13 states and the District of Columbia (Abacus). Which leaves three questions for any campus above the threshold: what the registry demands today, what the curtailment rejection leaves open, and which service class a new build should actually pursue. The October order answers the first; the second stays open, since PJM can try again; and the third comes down to a trade between service terms and self-supplied capacity.
What the Registry Actually Is
FERC accepted PJM’s definition of Large Load, “a customer with a cumulative peak load of 50 megawatts or more at either a single site or at multiple affiliated sites within a one-mile radius,” and found that definition “is just and reasonable and not unduly discriminatory or preferential” (Dominion Post). Cumulative, not per building. Affiliated sites inside a mile count toward the same trigger.
Cross it, and the registry collects six categories: locations, projected in-service dates, ramp schedules, peak demand, supply arrangements and backup generation (TechTarget). The threshold test fits in one terminal run:
# PJM Large Load test: cumulative peak (MW), campus plus affiliated sites within one mile
python3 - <<'EOF'
sites = [38, 14] # example peaks; replace with yours
print(sum(sites) >= 50)
EOF
As Jeff Shields, a PJM spokesman, told TechTarget: “FERC’s acceptance of our Large Load Registry and definition of large loads is a step in that direction” (TechTarget). Plenty of paper stands behind the step: PJM filed its 435-page proposal in August, drawing dozens of responses from utilities, states in its 13-state region, members of Congress and power customers such as Google, and FERC’s order runs 58 pages (Dominion Post). Docket ER26-3515 holds the order itself, accepting tariff revisions in part and rejecting them in part, with Commissioner Rosner concurring in a separate attached statement (FERC eLibrary).
What FERC Asked Every Grid Operator in June
October’s order did not arrive alone. On June 18, 2026, FERC invoked section 206 of the Federal Power Act to open show cause proceedings at all six regional grid operators it oversees, telling each to justify or revise its rules for connecting data centers and manufacturing facilities (FERC; Abacus). Each operator and its transmission owners got 60 days to show why existing tariffs stay just and reasonable without large-load provisions, or to file changes (FERC). A parallel 30-day deadline demanded an informational report on how each operator intends to ensure adequate generation for existing and new large loads (FERC). Commission staff reviewed more than 3,500 pages of public comments in the large load interconnection docket in developing the action (FERC).
About 2,289 GW of active interconnection requests sat in RTO and ISO queues at the end of 2024, down from roughly 2,368 GW in 2023, per the 2024 FERC State of the Markets report released in March 2025 (Abacus).

Why FERC Rejected the Curtailment Half
The rejected piece carries a name engineers will meet in filings: the Interim Resource Adequacy Service, with its bring-your-own-new-capacity provisions and related capacity-market changes (TechTarget). FERC turned it down over concerns about state jurisdiction over retail customers, the treatment of different customer groups, and PJM’s justification for the proposal (TechTarget).
PJM had argued that existing customers should not carry the costs and reliability risks of demand growth outpacing new generation, a position tied to its Ratepayer Protection Pledge, under which data centers and other large loads committed to support grid reliability and affordability (TechTarget). Stakes in that argument are measurable: The Brattle Group estimates that a 10% improvement in grid utilization would cut average retail rates by nearly 4% (Utility Dive). Commissioner Rosner’s concurrence pressed further, arguing that in an emergency, data centers not serving critical functions should be shut off before ordinary customers, as Dominion Post reported (Dominion Post). A commissioner’s view. Not the order’s.
Taken together, the registry’s approval and the curtailment rejection mean the October order increases visibility into large loads without handing PJM a federal tool to interrupt them.
Conditional Service or Self-Supply
SPP’s FERC-accepted framework shows what conditional service looks like for AI data center grid interconnection: service to large loads can be interrupted when transmission conditions require it, and a maximum seven-year term pushes customers to secure resources or finish network upgrades (TechTarget). Elizabeth K. Whitney, managing principal at Meguire Whitney, said FERC’s show-cause orders pointed to SPP’s large-load framework as a model for other grid operators (TechTarget).
What actually separates the two mechanisms? As Whitney told TechTarget: “The functional difference is that conditional transmission service is interrupted when thermal or voltage limits are exceeded, whereas a curtailment mandate is triggered when there is insufficient generation to meet load” (TechTarget).
For power procurement teams negotiating an AI data center grid interconnection, that defines the choice at any campus above the line: accept interruptible terms and budget around thermal and voltage events, or buy firmness on site with generation and storage. On the self-supply side of that decision, see Google Buys Nuclear Reactor Uprates, Not a New Reactor. Two prices, one decision.
What the Registry Does Not Verify
Nothing in the registry independently checks that a proposed facility has the infrastructure, financing or equipment to connect on schedule or hold its projected consumption (TechTarget). Intent, not capacity. As Neil Osnato, founder at Persistence Analytics Group, told TechTarget: “A reported 500 MW project is not necessarily 500 MW of executable, energized or persistent operating demand” (TechTarget). File ramp schedules and projected in-service dates that survive scrutiny, since the registry collects them as projections, not verified commitments.
That suggests the near-term consequence for developers is disclosure and forecast exposure, not forced load reduction; PJM would have to refile to obtain any new curtailment authority.
Run the Numbers, Then Pick a Service Class
Start with the market arithmetic. The average new build entered service in 2025 at nearly 80 MW (Abacus), against a registry trigger set at the 50 MW cumulative line (Dominion Post), which puts the typical build about 60 percent above the trigger ((80 − 50) ÷ 50 ≈ 0.6). Both inputs are megawatts, but the first is an average across facilities that entered service during 2025, so the comparison says a typical build clears the line, not that every new AI data center does.

Because the trigger sits below the average build, the registry reaches typical new large data centers rather than only exceptional ones.
What to Watch, and What to Do This Week
One more thread to track: the House has passed a ratepayer-protection bill aimed at data centers (Utility Dive). Meanwhile, four moves fit inside a week:
- Assign an owner to each of the six disclosure fields; ramp schedules and backup generation take the longest to defend.
- Price both service paths side by side before a utility prices one for you: interruptible terms against on-site generation and storage sized for thermal and voltage events. For the budget discipline that pairs with it, see Enterprise AI Budget: Tokenomics Foundation Aims to Measure, You Cap.
- Stress every projected in-service date against financing and equipment reality before it becomes a filed megawatt.
- Bookmark docket ER26-3515 in FERC’s eLibrary for whatever PJM files next.
Run the threshold check first: sum cumulative peak load across the campus and any affiliated sites within a one-mile radius, then compare the total against the registry threshold (Dominion Post). At or above it, draft all six disclosure fields, from ramp schedules to backup generation, before PJM asks (TechTarget). The average 2025 build clears that bar with room to spare. For the primary text, the order sits in FERC’s eLibrary under docket ER26-3515 (FERC eLibrary).